WSF advances electrification of aging ferries, contractor Vigor upgrades Wenatchee

Image credit: WSF

Washington State Ferries (WSF) is advancing electrification work at the Wenatchee shipyard to upgrade Wenatchee’s ferry aging propulsion system and conversion to hybrid-electric power. With capacity for 202 vehicles, the Wenatchee is the largest passenger ferry in the United States to be electrified. WSF originally estimated work would take roughly a year to complete and now expects a return to service summer 2025.

Major work completed to date on Wenatchee includes removal of two propulsion diesel generators, installation of electric power conversion and distribution equipment, upgrades to obsolete propulsion control equipment, reconfiguration of piping systems, and build-out of two new battery rooms.

Ongoing work includes installation of thousands of feet of electric and fiber optic cable. From there, the battery modules will be installed, and crews will begin to bring the ferry back to life. This “commissioning” process is a highly structured sequence of energizing system components and testing them to ensure they operate as designed.

WSF awarded a contract to Vigor in September 2023 to convert the Jumbo Mark II class ferries to hybrid-electric power and complete the required propulsion system upgrades, ensuring the vessels remain reliable for their 60-year lifespans. The three ferries, the Wenatchee, Tacoma and Puyallup, were built in 1998, 1997 and 1999 respectively. 

The Jumbo Mark II ferries are the biggest emitters in the fleet, contributing up to 26% of WSF’s greenhouse gas emissions. When conversions are complete and the terminals are electrified, Jumbo Mark II emissions are expected to drop by roughly 95%. The conversion of all three vessels and their supporting terminals will reduce WSF’s diesel fuel consumption by over 4.7 million gallons per year. The designs will support three modes of operation – diesel, battery or hybrid-diesel battery – providing increased reliability and resilience. 

Vigor's $150 million winning bid for the contract came in about $16 million under the second place bid but was still $30 million above the state’s $120 million estimate for the project. Vigor has been awarded $100 million for the conversion of two vessels, with a fixed-price option to convert the third vessel in 2025.

After Vigor’s work is complete, the WSF team will need approximately four weeks to put Wenatchee through its paces with additional system checks and sea trials, as well as training for the vessel crews. The Tacoma conversion will not begin until the Wenatchee returns to service.

If fully funded, the WSF Electrification Program will convert six current diesel ferries to hybrid electric, build 16 new hybrid vessels, retire 13 diesel ferries, and add charging power to 16 terminals. Legislators have so far appropriated $1.7 billion from the Move Ahead Washington package and Climate Commitment Act for three ferry conversions, five new hybrid-electric ferries and electrification at five terminals including Colman Dock. The total electrification program will cost almost $4 billion.