SEPTA awards ADA Improvement design contract to facilitate competitive funding request
SEPTA has awarded a $5,793,063 contract with Jacobs Engineering Group, Inc. (Jacobs) to advance accessibility improvements on three subway stations to 100 percent. Commencing design allows SEPTA to pursue competitive funding specifically for accessibility improvements at legacy rail stations.
Jacobs will provide architectural, design and construction-related services for the Lombard-South and Ellsworth-Federal Stations on the Broad Street Line, and the Chinatown Station on the Broad-Ridge Spur. These stations were built decades before the enactment of the Americans with Disabilities Act (ADA) and are only accessible via stairs.
Station accessibility is a core component of the Strategic Plan, SEPTA Forward. Once design is completed, SEPTA can advance on the construction phase to make the stations fully ADA accessible and in a state of good repair (SGR) with elevator installation; platform renovation; new signage, lighting, and security cameras; and waterproofing.
SEPTA has prioritized accessibility on both the Market-Frankford Line and Broad Street Line in its 12-Year Capital Program. SEPTA has nearly completed the ADA improvement project at Susquehanna-Dauphin Station, and is undertaking construction at the Tasker-Morris Station. The timelines for work at other stations on the Broad Street and Market-Frankford Lines will be announced with the release of the new capital budget and program in April.
Source: SEPTA