Metrolinx releases environmental review report for Dundas BRT Mississauga East segment

Image credit: Metrolinx

Metrolinx has released an Environmental Project Report (EPR) for the Dundas bus rapid transit (BRT) Mississauga East segment for public review until March 25. After that, there will be a 35-day Minister’s review period from Mar. 26 to Apr. 28, 2022.

The Dundas BRT corridor will span 48 km on Dundas Street from Highway 6 in Hamilton to the Kipling Transit Hub in Toronto, linking Etobicoke and Mississauga City Centres. Over 20-km of the route would feature bus lanes in a dedicated right-of-way.

The project is divided into four segments:

  • Toronto – Kipling Transit Hub to Etobicoke Creek;
  • Mississauga East – Etobicoke Creek to Confederation Parkway – the current phase;
  • Mississauga West – Confederation Parkway to Ninth Line; and
  • Halton and Hamilton – Ninth Line to Highway 6

The next area of focus for the Dundas BRT project will be on the Toronto and Mississauga West segments.

Source: Metrolinx