MCDOT to launch first phase of Ride On Reimagined Plan in June 2025

Image credit: MCDOT

The Montgomery County Department of Transportation (MCDOT) will launch first phase of the Ride On Reimagined Service and Implementation Plan in June 2025. The plan will modernize the bus network over several years to improve service efficiency and route alignment. By 2030 and beyond, the plan envisions expanded Bus Rapid Transit (BRT), new micro-transit zones, and increased service frequency, contingent upon funding availability.

The plan is the culmination of over two years of research, coordination and development. The effort examined the transit landscape of Montgomery County, including MCDOT Ride On and Metrobus service. Ride On operates over 80 bus routes, many of which have been unchanged since their implementation in the 1970s, making this redesign a vital process to align with the current and future needs of riders.

The implementation of the Ride On Reimagined Service and Implementation Plan will take place in phases over the next several years. The key changes and benefits are as follows:

YEAR 1: Immediate Changes (June 29, 2025) - The first phase of implementation will occur this summer and focus on changes that will immediately improve service.

  • New and Adjusted Routes: Route realignments will reduce redundancy and improve efficiency.
  • Great Seneca Transit Network (GSTN): Ride On extRa Lime and Pink routes launched in fall of 2024 as phase 1 of the GSTN.
  • Service Enhancements Within Current Budget: Improvements will focus on increasing service frequency and optimizing routes without requiring additional funding beyond the current budget allocations
  • WMATA & Local Transit Integration: Coordination with WMATA’s Better Bus Network Year 1 changes

YEAR 5: Network Expansion (2030) - By the 5-year mark, Ride On bus service will have a visibly restructured route network for better coverage and efficiency. Network changes progress as resources become available and are dependent on a funding increase of 5% per year after Year 1.

  • BRT Expansion and New Connections: Implementation of MCDOT’s Flash MD 355 (Phase 1) and Viers Mill Road BRT projects.
  • Purple Line: Expected completion and full operation by Year 5.
  • Ride On Flex Service: Eight new proposed Flex micro-transit zones, providing on-demand, flexible travel options for areas with lower ridership demand.
  • Route Modification: Several routes will have changes for more direct connections to reduce travel times and expand weekend service.

THE VISION NETWORK: Future Growth – It represents the full, ideal build out of Montgomery County’s transit network with all possible proposed improvements. Progress is dependent on the availability of funding will be implemented in phases as new funding sources become available.

  • Stronger coordination with WMATA and MTA to ensure a connected transit network.
  • Full implementation of the Flash BRT network along high demand corridors with 8 new BRT lines and 4 new high-capacity Ride On extra lines.
  • Expansion of Ride On’s flex service through 19 new Flex zones
  • Over 30 routes will have improved weekday frequencies and 38 routes will have improved weekend frequencies
  • 26 routes will have new weekend service
  • GSTN will be fully implemented
  • Improved access and travel times to key destinations throughout the County.

Source: MCDOT