VTA completes two major maintenance projects across light rail system

Image credit: VTA

The Santa Clara Valley Transportation Authority (VTA) light rail system is coming up on 40 years of service and needs ongoing maintenance. Over the summer, crews worked to complete two milestones for the agency. Both projects are part of VTA’s 2025 rehabilitation efforts.

At Woz Way/San Carlos Junction in June, crews worked to realign the track junction and overhead power system. This work also prepares the area for “future service options, such as a Santa Teresa to Winchester route.”

In July, crews worked on a grade crossing at Capitol Avenue and McKee Road. The crossing was replaced with a new design that is built “to handle both trains and heavy street traffic for nearly 40 years.”

The rehabilitation works include upgrades to signals and new crossovers at both Champion and Bonaventura stations. VTA says out of its 200 crossings, 10 have been replaced with another eight are scheduled for the “near term.” The next project is in the Mabury area scheduled for October where crews will work to install a new crossover.

 

Source: VTA