Santa Clara VTA progresses BART Silicon Valley Extension Phase II Project

Image credit: VTA

San Clara Valley Transportation Authority (VTA) is in design and engineering phase of the project to extend Bay Area Rapid Transit (BART) service from the Berryessa Transit Center to stations at 28th Street/Little Portugal, Downtown San José, and Diridon Station.

Throughout 2025, VTA reached “key milestones” that have set up advancement in 2026. This includes expanded construction activity and tunneling preparations. Last year, VTA secured $100 million in state funds for the project, confirmed its choice for a single-bore tunnel method, and procured the tunnel boring machine (TBM).

“2025 was about building the foundation,” said Tom Maguire, VTA’s Chief Megaprojects Delivery Officer. “That work allows us to accelerate toward major construction and keep this critical regional project moving forward in 2026.”

Now, VTA states more than 70% of the tunnel launch structure walls are complete at Newhall Yard. This also includes the Caterpillar Shaft, also known as the deepest part of the structure. In 2026, VTA will continue its work constructing the tunnel launch structure with utility relocations and staging-area development early construction activities.

BART Silicon Valley Phase II Extension Project (BSVII Project) is Santa Clara County’s largest public infrastructure project. The BSVII Project is a six-mile extension of the regional BART system from Berryessa/North San José Station to the City of Santa Clara. With four stations, the project will serve 55,000 weekday riders, providing a fast and convenient transit option and improving connections to other regional transit services.