Valley Metro testing along entire South Central Extension Downtown Hub route
Valley Metro and the city of Phoenix are continuing preparations for opening of the South Central Extension/Downtown Hub (SCE/DH) project on June 7. As testing advances into the next phase, the community will notice increased train activity in downtown Phoenix and along south Central Avenue.
The 5.5-mile extension will operate between downtown Phoenix along Central and 1st avenues, continuing south to Baseline Road. The expansion will also introduce a two-line rail system intersecting at the new transit hub in downtown Phoenix:
- A Line: Operating between Gilbert Road/Main Street in Mesa and the Downtown Hub
- B Line: Operating between Metro Parkway in northwest Phoenix and Baseline Road/Central Avenue
The Downtown Hub consists of four platforms on Washington, Jefferson, Central and 1st avenues where riders will transfer between the A and B lines.
A reality in 2025 instead of the originally planned 2034 opening date, the South Central extension also brings with it new and improved public infrastructure. Project features include eight new stations, 14 new trains, 110-space park-and-ride facility at Baseline Road/Central Avenue, enhanced bike lanes and pedestrian pathways, over 550 new trees and desert-adapted landscaping providing much-needed shade, and comprehensive utility upgrades replacing more than 30 miles of underground infrastructure. This expansion also introduces modern infrastructure improvements including 18 community-driven public art installations created by artists who are predominantly local.
Selected as a priority corridor after a comprehensive analysis, the SCE/DH light rail expansion addresses critical transportation needs in an area where 44% of residents have limited or no access to personal vehicles. The extension connects historically underserved communities to regional destinations, including downtown Phoenix, the airport area, educational institutions and key employment centers. The new extension is expected to add more than 8,000 daily riders to the light rail system, which currently serves approximately 35,000 boardings per day.
With federal grants covering more than half the project's $1.34 billion budget, additional funding sources include Phoenix Transportation 2050 and regional Proposition 400 funds. Valley Metro and the City of Phoenix, alongside construction contractor Kiewit, implemented targeted workforce development initiatives creating economic benefits for the local community. Future economic development in the area will be guided by the South Central Transit-Oriented Development Community Plan, approved by Phoenix City Council in spring 2022.
Source: Valley Metro