Santa Clara VTA reenters CIG New Starts Program for BART Silicon Valley Ext Phase II

Image credit: VTA

The Federal Transit Administration (FTA) has notified the Santa Clara Valley Transportation Authority (VTA) that Phase II BART Silicon Valley Extension Project has been approved to re-enter the federal Capital Investment Grants New Starts Funding program.

This approval allows VTA to:

  • Apply for twice the amount of funding anticipated under the previous Expedited Project Delivery pilot program. VTA has authority to pursue federal funding for up to 50 percent of the cost of Phase II. The funding could be as much as $4.6 billion.
  • Receive reimbursement for past eligible expenses back to March 2016, and all remaining work for the estimated total project cost of up to $9.3 billion.

VTA plans to begin the federal funding application as soon as summer 2023 after a final cost estimate and funding plan is worked out. VTA is seeking an additional $750 million from the state’s transportation funding program for major transit projects as the last key funding piece.

Phase II Extension includes six miles of track and four stations to extend heavy rail service from Berryessa/North San Jose through downtown San Jose into Santa Clara. VTA is embarking on the first rail project in the United States to be constructed by a single bore, allowing both tracks and station platforms to be constructed within the tunnel, utilizing the newest technology in underground construction.

Kiewit Shea Traylor has the tunnel and trackwork contract and plans to procure a tunnel boring machine, 54 feet diameter, to bore a five-mile tunnel under downtown San Jose. With consideration of the FTA’s actions, VTA’s Board of Directors authorized the execution of contract amendments for up to $460 million, including the purchase of the tunnel boring machine and early construction activities.

 

Source: VTA