Met Council and Hennepin County agree on METRO Blue Line LRT extension funding
Metropolitan Council members and the Hennepin County Board of Commissioners approved a grant agreement that will provide $75.3 million in county funds for the METRO Blue Line Extension Light Rail Project to keep project work going through the end of 2024.
The funding will allow the project to:
- Continue engineering and consulting services necessary to advance design and environmental analysis
- Continue extensive outreach and engagement efforts
- Advance implementation of strategies to build community prosperity and prevent displacement
- Update ridership projections
- Prepare an updated cost estimate and schedule
- Prepare plans and other technical information required to seek municipal consent from cities along the corridor.
The funding agreement also establishes a governance process for the project and identifies responsibilities between Hennepin County and the Metropolitan Council.
Agreement makes major changes in governance compared to previous transitway projects:
- The pact authorizes agreements with funding partners for each project phase
- A new governance model, the Project Decisions Board, will be formed to approve and authorize major project decisions. The new board will be made up of two county commissioners, one commissioner from the regional railroad authority and two Metropolitan Council members
- An integrated project office with staff from both Hennepin County and Metropolitan Council leadership roles will continue to work collaboratively to deliver the project
- Streamlined reporting and processes will be implemented that maximize efficiencies for both parties
- Financial roles are clarified.
Financial responsibilities are spelled out between the Council and Hennepin County:
- The Council will be responsible for federal funds in a future Full Funding Grant Agreement (FFGA), with its contributions limited to FFGA and any funds provided to Council specifically for Blue Line Extension. The Council is also responsible for future operations and capital maintenance (not covered in this Capital Grant Agreement)
- Hennepin County is responsible for the local share of funding in engineering and construction phases, including project start-up costs
- Through the new Project Decisions Board, both parties have approval of project budget, contract awards and change orders.
The action approved by the Council authorizes the project team to advance design plans and complete the municipal consent process beginning in summer 2024 to confirm the final route.
Source: Met Council