Caltrain, Balfour Beatty and PG&E energize full 51-mile Caltrain Corridor
Caltrain, with its partners Pacific Gas and Electric Company (PG&E) and Balfour Beatty, has successfully energized and tested the full 51-mile Caltrain-owned corridor between San Francisco and San Jose. This milestone achievement in the Caltrain Electrification Project signifies major progress in expanding Caltrain’s ability to test electric trains at full speed along the corridor and prepare for electrified revenue service in September 2024.
Caltrain has built two main traction power substations, one in San Jose and the other in South San Francisco. Together, with one switch station and seven parallel stations along the corridor, power substations provide, distribute, and regulate electricity to the overhead wires which will power Caltrain’s new high-performance electric trains.
PG&E infrastructure upgrades include:
- Constructing two, double-circuit 115 kV transmission connections from the East Grand Substation in South San Francisco and the FMC Substation in San Jose to Caltrain traction power stations in those communities.
- Rebuilding the East Grand and FMC substations that enabled PG&E to support Caltrain’s request for redundant transmission feeds.
- Upgrading three PG&E and two third-party remote end substations.
Caltrain’s historic Electrification Project is the first undertaking in North America in a generation in which diesel trains and their infrastructure components are transitioned to an electrified system. Electrification will also help meet climate action goals and set the framework for future High Speed Rail network that will run on the Caltrain corridor.