OC Transpo Stage 2 O-Train Line East Extension achieves substantial completion
The Independent Certifier has issued the Certificate of Substantial Completion for Stage 2 O-Train Line East Extension. Substantial Completion is an important contractual milestone and confirms that the constructor, EWC, has delivered all new system infrastructure and that it is functional and can be safely operated and maintained. This comes after the City of Ottawa and the Independent Certifier conducted a detailed review of EWC’s submission.
Steps to passenger service:
- Step 1: Testing and Commissioning (done)
- Step 2: Substantial Completion (done)
- Step 3: Trial Running
- Step 4: Final system preparation
- Step 5: Passenger service
Having achieved Substantial Completion, Rideau Transit Maintenance (RTM) now assumes responsibility for the maintenance of the new East Extension. There will be a period of startup and familiarization for RTM, as they take over the maintenance of the new infrastructure. This familiarization period is a best practice from the preparations to successfully launch O-Train Lines 2 and 4.
As with any major construction project, there will be activities that will continue after Substantial Completion. On the East Extension, these include:
- Updates to the train control system software prior to Revenue Service
- Adjustments to the platform edge cameras to optimize their performance
- Landscaping, final paving on Highway 174 and other final works
This milestone is a significant step towards connecting east end communities to downtown and western neighbourhoods through the existing train system. Over the coming days, OC Transpo will continue to work with RTM during the handover and their startup phase. The East Extension is scheduled to launch in Q2 2026.
In parallel, work continues to safely restore full capacity and fleet availability on the existing Line 1. OC Transpo and Rideau Transit Group are working to complete new containment and monitoring measures for the Cartridge Bearing Assemblies that would allow the full fleet to be safely returned to operations. This will also allow Trial Running to commence. A technical briefing will be held to provide information and timelines once plans are finalized.
Source: OC Transpo