NORTA advances major infrastructure projects
The New Orleans Regional Transit Authority (NORTA) is advancing several major infrastructure projects aimed at improving reliability, accessibility, and the rider experience. Here’s the latest on three projects currently underway:
The long-anticipated Renovation of the Algiers Point Ferry Terminal is transforming the facility into a more accessible and welcoming space for riders, ferry operations, and the surrounding community. The project follows an extensive planning and community engagement process that began in 2024 and includes improvements to the terminal building, passenger boarding areas, accessibility, and surrounding site.
Construction is now 55 percent complete, with building framing completed and new windows installed. Site work is approximately 35 percent complete and continuing. The project is still on schedule for completion in First Quarter 2027.
The Harmony Circle Track Replacement Project was launched to address deteriorated track conditions that had affected service along the St. Charles Streetcar Line. The work was part of RTA’s coordinated rail improvement efforts focused on strengthening the reliability of this historic transit corridor.
Track replacement work at Harmony Circle was completed in August, allowing streetcar service to resume through the area and ending the temporary bus bridge that had been running during construction.
Work also continues on the Carrollton Double Crossover Project at the Claiborne Avenue terminus of the St. Charles Streetcar Line. The project will relocate sections of rail and overhead electrical infrastructure to support future ADA accessibility improvements at the streetcar stop.
Construction is now 40 percent complete. Rail demolition, removal of the catenary line, and subsurface drainage work have been completed. The project is on schedule for completion in December 2026.
Source: NORTA