LA Metro Pomona to Claremont A Line Extension enters preconstruction

Image credit: LA Metro

The Pomona to Claremont A Line Extension is underway with final design and pre-construction. Parsons continues to advance the project design towards its next milestone of 60 percent, which remains on schedule to be ready for review in early January 2027. From there, the design will progress to 85 percent and 100 percent before reaching “Approved for Construction” drawings.

The Foothill Gold Line from Glendora to Montclair will extend the Metro A Line 12.3 miles and add stations in the cities of Glendora, San Dimas, La Verne, Pomona, Claremont, and Montclair – and will be built in phases. Once completed, a trip from Montclair to downtown Pasadena will take just over 40 minutes and further to Los Angeles will take approximately 67 minutes.

Work is now underway to ready the 2.3-mile Pomona to Claremont A Line Extension for construction. Two major contracts needed to deliver the project have been awarded – the first for design and engineering services, and the second for the construction manager. Final design and preconstruction activities are now underway. The project will add a new Metro A Line station in the city of Claremont.

To support the design effort, Parsons attends regular task force meetings on different project elements (track, civil, utilities, structures, stations, etc.) with Construction Authority staff and consultants, meets with the corridor cities and other third-party agencies, and continues to deploy survey crews throughout the 2.3-mile corridor to collect data on existing conditions. Starting in October, crews will be collecting geotechnical borings to understand the soil conditions under the project corridor and at the street crossings where future bridges will be built for the project.

SSH JV continues to support the project by providing feedback on the design, working with the Construction Authority to find ways to reduce risk and costs on the future construction effort, developing an overall construction schedule, preparing programmatic plans, conducting field reviews and developing early work package recommendations. All of this is part of the pre-construction phase of their work that will be ongoing through all of 2026 and much of 2027.

The SSH JV is under contract for the initial pre-construction work phase and will have the opportunity to negotiate a construction contract to build the Pomona to Claremont A Line Extension with a guaranteed maximum price once the design reaches 85 percent. That process will conclude in Fall 2027, with major construction expected to begin in late 2027 and take approximately four years.

The LA Metro reported that since opening the four new stations from Glendora to Pomona one year ago, ridership on the A Line is up more than 14 percent, helping support a 12 percent increase in rail ridership systemwide over the same period the year before.