JTA completes MobilityWorks 1.0 Program, advances MobilityWorks 2.0

Image credit: JTA

The Jacksonville Transportation Authority (JTA) celebrated completion of the final MobilityWorks 1.0 project, roadway and transit enhancements along San Pablo Road from Beach Blvd. to Atlantic Blvd.

The project, which began in May 2022, included reconstruction of the existing roadway from a two-lane to a three-lane, divided urban section from Beach Boulevard to Crystal Cove Drive and from Osprey Point Drive to Atlantic Boulevard.

JTAMobilityWorks was designed to complete projects funded by the extension of the Local Option Gas Tax in 2014. JTA has now completed all 13 roadway projects and 14 mobility corridors initiated under MobilityWorks across Jacksonville.

In March 2023, JTA launched MobilityWorks2.0, another series of 17 projects meant to enhance transportation and mobility throughout the city while investing $494 million in local option gas tax revenues back into the city’s infrastructure. The projects will be constructed over the next 30 years, with project completion anticipated by 2052.

The Countywide Transit Enhancements project will improve accessibility by making the JTA system fully Americans with Disabilities Act (ADA) compliant. This project includes improvements to all bus stops in Duval County that are ADA non-compliant. Improvements will be made at 823 bus stops and include installing new concrete bus pads, shelters, and amenities at existing bus stops. The projects are estimated to cost $34.7 million.

During 2023 and 2024, the project advanced ahead of schedule and a total of 197 bus stops have been completed so far. In 2023, the goal was to complete 55 bus stops and 73 bus stops were completed. In 2024, the goal was to complete 55 bus stops but 124 bus stops were completed. Construction will continue in 2025 with upgrades at 85 bus stops.

Source: JTA